docketplan takes the retention off each payment application by fixed rules, with no AI. You say how much the subcontract holds. Only the owner or a contracts manager can set it.
Open the job's details
Select the job switcher at the top left. Select Job details.
Select Edit job details.
Say what the subcontract holds
Under Retention, look at Does the subcontract hold retention?. Select Yes.
In Percentage held, type the percentage. It can be from 0.01 to 20. It is taken from the gross to date on each application.
If the subcontract sets a limit, type it in Limit (€, optional). If it sets none, leave it empty.
The Retention card.
If a payment application is approved and not sent, saving takes it back to a draft. docketplan says so before you save. A sent application never changes.
Select Save changes.
The next payment application shows the retention, and the retention held to date.